Les Diamants Stornoway
MINING AND METALLURGY
2015-2016
Power plant piping, mechanical, electrical and instrumentation installation. A seven-generator unit, including gas pipes, glycol and tanks, pumps, compressors and heat exchangers. The electrical panel and instrumentation; equipment, electrical room wiring, main and oil stations, interior and exterior.
-
Goldcorp – Eleonore Project
Mining, metallurgy, Industrial piping and electricity
2013-2014
Installation of piping and mechanical equipment for the concentrator, paste backfill plant and primary and secondary crushers (ball mill, conveyors, tanks, thickeners, pumps).
-
Detour Gold
Mining, metallurgy, Industrial piping and electricity
2011-2012
Installation of piping, electrical and instrumentation equipment for the ore processing plant, including commissioning and operating areas (ball mill, cyclones, tanks, chemical treatment, carbon regeneration kiln and refinery); installation and maintenance of power lines and substations.
Furthermore, we completed the electrical power installation, including the electrical rooms.
-
Canadian Royalties
MINING AND METALLURGY
2012-2013
Mechanical, piping and boiler-making installation for the ore processing plant. The work done includes the installation of four ball mills, including hydraulic piping, erection/installation of process tanks, installation of the crushing system (jaw crusher, conveyors and transfer chutes) and installation of process piping in the reject thickener building.
-
Québec Lithium
MINING AND METALLURGY
2012
Electrical, mechanical piping and boiler-making installation for an ore processing plant to produce Lithium. The work done includes power electricity for the mill and crusher, installation of crushing equipment (jaw crusher, cone crusher, conveyors, screens, transfer chutes, etc.), installation of a dust collection system and process/hydraulic piping.
-
Mosaic Potash
EXPANSION PROJECT COLONSAY 50D
Saskatchewan, Canada
2011Installation of piping, ducting, ore passes and mechanical equipment for the plant’s screening facilities: bucket elevators, belt conveyors, screw conveyors, ROTEX screens, fans and dust collectors.